Structural work
S 1 |
Earthwork for the access road |
2 days |
|
S 2 |
Earthwork for the house foundation |
3 days |
|
S 3 |
House foundations |
2 days |
|
Concrete drying |
7 days |
||
S 4 |
Basement building |
10 days |
|
Basement drying |
5 days |
||
S 5 |
Floor preparation Electricity preparation |
3 days |
|
S 6 |
Pour the Slab |
1 day |
|
Slab drying |
5 days mini |
||
S 7 |
Walls construction |
7 days |
|
Walls drying |
7 days |
||
S 8 |
Second floor preparation |
3 days |
|
S 9 |
Pour the second floor slab |
1 days |
|
Slab drying |
5 days mini |
||
S 10 |
Basement preparation |
2 days |
|
S 11 |
Pour the basement slab |
1 day |
|
Basement slap drying |
4 days |
||
S 12 |
Gable and moulding builting |
4 days |
|
Drying |
5 days |
||
S 13 |
Frame assembly |
7 days |
|
S 14 |
Roof covering |
3 days |
|
S 15 |
Zinc work |
3 days |
|
S 16 |
Windows and Doors installation |
4 days |