Installation of the energy grids
E1 |
Electric pipe placement |
1day with S 5 |
|
E2 |
Electric pipe placement |
1day with S 8 |
|
E3 |
Electric wiring |
10 days |
|
E4 |
Installation of the electric devices |
2 days |
|
E5 |
Water pipe placement |
6 days |
|
E6 |
Installation of the sanitaries |
2 days |
|
E7 |
Heating installation (boiler, radiator...) |
10 days |